Really need help on ITTOs
Submitted by anand2381 on Thu, 04/19/2012 - 15:17
Guys,
I'm able to understand all the concepts of all knowledge areas and answer all scenario questions correctly from mock exams but not able to answer ITTO questions as they are confusing and really worried.
Is there any way to remember ITTOs? Any strategy to remember?
Really need help on this from you guys..My confidence level is low because of ITTOs.
Please help..
milind
Thu, 04/19/2012 - 16:00
Permalink
Do not loose confidence
Used http://www.brainbok.com/home#ITTO to go through Inputs and Outputs for processes.
I used following method to remember ITTO:
A)
12.Estimate cost DEOX
bp-vc-rtpae
13.Develop budget DOX
frech
36. Control cost
CDOPUo
Eft-vp-p
C- Change Requests ,D-Project Documents Updates (Output), P – Project management plan updates
E –EEF (Input),O – OPA (Input) ,
Ue – EEF Updates , Uo – OPA Updates ,
X – Expert judgment
--- Prepare procument ITTO sepeartely because they are very logical.
B)
Cost tools : EPABTRCV CREFH and PVPEFT
Scope tools : DRTE PDM/DD/LL/SN EPAPB EAPTR WARCCSSS PVPWARSS
If u observer PVP is same. And "WAR" is easy to remember.
In this way within 2-3 days u will remember all.
Hope this will help u.
rajapavani
Tue, 04/24/2012 - 18:50
Permalink
Dumpsheet!!
I am glad that the dumpsheet that I prepared is helping you. If you would like, I can send you the notes as well.
Knowledge areas
Initiating Phase
Planning Phase
Execution
Monitor and control
Closing phase
Integration management
6
Project charter
EOX
3.Develop project management plan
EOX
23.Direct and Execution
CDEPOX
‘pmis’
31. Monitor and control CDEPOX
32. Perform Integrated control
CDEPOX
41. Close project or phase
OUoX
Scope
5
4.Collect ----Requirements
5.Define scope DOX apef
6. WBS DO Decompose
33. Verify scope CD inspection
34. Control scope CDOPUo variance analysis
Time
6
7.Define activities EOX red-t
8.Sequence activities DO pads
9.Estimate activity resources DEOX
bppae
10Estimate activity durations DEOX
rtpae
11.Develop schedule DEO
Sc-sc-wars
35. Control schedule
CDOPUo
Vp-sp-wars
Cost
3
12.Estimate cost DEOX
bp-vc-rtpae
13.Develop budget DOX
frech
36. Control cost
CDOPUo
Eft-vp-p
Quality
3
14.Plan quality DEO
Bench, coq, cost/b/a, doe, Fcharts, methodologies, stats sample, additional tools.
24.Quality assurance
CDPUo
37. Quality control
CDOPUo
Human resources
4
15.Develop human resources plan EO
ono
25.Acquire team EOP avpn
26. Develop team Ue itc-grt
27. Manage team COP UeUo cop-ii
---------
-
Communications
5
Identify stake holders
EOX
16. Plan communications DEO
Four c ( Reqs, tech. Models, methods)
28. Distribute information
Ouo ci
29. Manage stake holders
CDOPUo cim
38. Report performance
COUo f-vcr
Risk
6
17. Plan Risk management EO meet and analysis
18.Identify Risks EOX cdesaid
19. Qualitative risk analysis OX 4epr
20. Quantitative risk analysis OX edq
21.Risk response DPX ssce
39. Monitor and control risks
CDPUo 3r-vts
Procurements
4
22.Plan procurements CEOX mec
30. Conduct procurement
CDOPX bp-pae-ii
40. Administer procurements
CPUo 3p2cir
42. Close procurements Uo
C- Change Requests ,D-Project Documents Updates (Output),E –EEF (Input),O – OPA (Input) ,P – Project management plan updates , Ue – EEF Updates , Uo – OPA Updates ,X – Expert judgment
Bbolo84
Thu, 04/26/2012 - 17:39
Permalink
Dumpsheet
Hello,
Could you send the dumpsheet to my email? Its coreyc.black@gmail.com
Thanks!!
saket_pmp
Thu, 04/19/2012 - 19:15
Permalink
PMP IITO learning strategy
I am a PMP instructor and have been conducting PMP workshop over 2 years. The question you have asked is a common question and I answer this way to all:
Choice is yours, I am sure you will find your own ways. J