Q5 Question : Project Plan includes:
1. List of milestones
2. Cost and Schedule Baselines
3. how changes will be monitored and controlled
4. All of the above
Correct Choice: 4
Forums:


rishabhjain23
Thu, 08/18/2011 - 20:34
Permalink
2. Cost and Schedule
2. Cost and Schedule Baselines
devgopi
Thu, 08/18/2011 - 21:21
Permalink
4. all of the above, is it
4. all of the above, is it it?
rishabhjain23
Fri, 08/19/2011 - 06:05
Permalink
yeah it should be All of the
yeah it should be All of the above