QUICK10, LITTLE TOUGH

1. What is the primary risk with including reserves or contingency allowances in your cost estimate?

a.

Cancelling your project

b.

Understating the cost estimate

c.

Overstating the cost estimate

d.

Tracking the funds

2. Which of these is not a typical constraint on the project team's personnel options?

a.

Organization structure

b.

Collective bargaining agreements

c.

Physical location

d.

Economic conditions

3. The most detailed level of the WBS is called the _______________ .

a.

WBS element

b.

Work package

c.

Project scope

d.

Deliverable

4. Two of the organizational process assets updated as a result of the Close Project or Phase process are:

a.

Project management plan, project charter

b.

Project charter, project calendar

c.

Project management plan, RBS

d.

Project management plan, risk register

5. Which of these precedence relationships is least commonly used in Precedence Diagramming Method?

a.

Start to Start

b.

Finish to Finish

c.

Finish to Start

d.

Start to Finish

6. If you are measuring the quality of an item on a pass/fail basis, what is that called?

a.

Attribute

b.

Tolerances

c.

Variable

d.

Prevention

7. Which term best describes the Identify Risk process?

a. Finite

b. Redundant

c. Iterative

d. Inconsequential

8. Which of the following defines the total scope of the project and represents the work specified in the current approved project scope statement?

a. Work Breakdown Structure (WBS)

b. Bill of Material (BOM)

c. Project Charter

d. Requirements Breakdown Structure (RBS)

9. What is the traditional way to display a reporting structure among project team members?

a. Text-oriented role description

b. Flowchart

c. Hierarchical-type charts

d. Matrix based responsibility chart

10. When would Rolling Wave Planning be useful in a project?

a. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.

b. You should use Rolling Wave Planning to determine the correct sequencing for long term items.

c. You should use Rolling Wave Planning to help you organize team member's activities within a large project group.

d. You should use Rolling Wave Planning to help you determine which activities are more important and should be done first.

aren't these all from Chris Scordo's book(Lite Mock # 1)?

These are for those,who havnt this material/those who could not be a member of e-read PMI.

It is also to materialise some discussion makes it better to understand in case of varing doubts.

Regards

 Hi Pawar

Can you also share the answers to these questions. I would like to verify my answers for these questions  :-)

  1. C
  2. C
  3. B
  4. D
  5. D
  6. A
  7. C
  8. A
  9. C
  10. A

Respected Pawarji Sir,


 


I scored 9 out 10.


 


I hope I did well. My wrong answer was 9.


 


Thanks,


KK...

I got 7/10

Great Saurabh especially you have not even touched PMBOK even for once.


 


Great!!!


 


KK...