Question on SPI

Hi,

 

I had a question on SPI. 3-year project finished 4 months early. What is the final SPI?

My calculations based on my understanding is 1.125 (rounded to 1.13) which I would choose no. 2 as my answer but the correct answer indicated on the test question is no. 4 which is "1". 

So am I right or the standard answer generated is wrong?

I think its 1.

SPI=EV/PV

earned value and planned value are both 100% at project completion.So it should be 1.

Thanks

 

I think its 1.

SPI=EV/PV

earned value and planned value are both 100% at project completion.So it should be 1.

Thanks

 

Very correct

Yes, I went to read further and tried to understand the formulae. My mistake was being mis-led by the early finish figure.

Thanks!