Question on SPI
Submitted by dr_retro02 on Sat, 01/05/2013 - 04:07
Hi,
I had a question on SPI. 3-year project finished 4 months early. What is the final SPI?
My calculations based on my understanding is 1.125 (rounded to 1.13) which I would choose no. 2 as my answer but the correct answer indicated on the test question is no. 4 which is "1".
So am I right or the standard answer generated is wrong?
Forums:


sunitaPMP
Sat, 01/05/2013 - 04:45
Permalink
I think its 1.SPI=EV/PVearned
I think its 1.
SPI=EV/PV
earned value and planned value are both 100% at project completion.So it should be 1.
Thanks
sunitaPMP
Sat, 01/05/2013 - 04:45
Permalink
I think its 1.SPI=EV/PVearned
I think its 1.
SPI=EV/PV
earned value and planned value are both 100% at project completion.So it should be 1.
Thanks
sspawar
Sat, 01/05/2013 - 07:23
Permalink
Very correct
Very correct
dr_retro02
Sat, 01/05/2013 - 07:19
Permalink
Yes, I went to read further
Yes, I went to read further and tried to understand the formulae. My mistake was being mis-led by the early finish figure.
Thanks!