Question solve it please

Jack is the project manager of a project and is looking at the schedule of work. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. The most likely reason that may need him to do this is:




  1. Add a note hereMany of the work packages have been completed and he wants to change the dates on subsequent ones.



  2. Add a note hereHis manager has requested him to change the milestone dates.



  3. Add a note hereTo allow time for a project status presentation.



  4. Add a note hereTo regulate expenditure of funds so that they can be reconciled against the disbursement of funds for the project.


answer is D but i thought it should be A, why it is D ? Pls explain. Thanks.


You are setting up your team for the project you are currently working on and you are looking at a chart that shows the programming will be performed by Systems Development, the infrastructure will be implemented by Infrastructure Systems, the customer communication will be handled by the call center. This is an example of what type of chart?




  1. Add a note hereRACI



  2. Add a note hereOrganizational Breakdown Structure (OBS)



  3. Add a note hereWork Breakdown Structure



  4. Add a note hereResource Breakdown Structure (RBS)


the answer according to my understanding should be A but correct answer is B why ?

 Hi Amber,

For question 1 refer to funding limit reconciliation under determine budget.

for question 2 refer to organizational charts/hierarchical charts under develop HR plan.