Question on SD- Oliver Lehman 75 Q
A project manager made 3-point estimates on a critical path and found the following results:

Opti. MostLikely Pessi. PERT Weighted avg
Acti A 12 15 24 16
Acti B 8 9 14 9.7
Acti C 15 19 27 19.7
Acti D 10 14 18 15.7
Acti E 17 20 35 22.0
Estimate for Critical Path 83.1
Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?
| App. 4.2 days | ||
| App. 5.2 days | ||
| App. 6.2 days | ||
| You can not derive the path standard deviation from the information given. | ||
Please suggest how to calculate?


Sharma
Sun, 05/27/2012 - 22:00
Permalink
another question
Q 31. Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
Network Diagram Image
What is the minimum total duration between the milestones A and B?
sspawar
Sun, 05/27/2012 - 23:12
Permalink
both q has been described and discussed in this forum
Dear Mr. Sharma,
Refer old posts of this forum - just by name - Oliver Lehmann or SD OR PERT OR NETWORK DIAGRAM, you will find your answer there.
if not then tell me ,
Regards
projmanpro
Mon, 05/28/2012 - 05:14
Permalink
See this thread of mine in
See this thread of mine in another forum, i explained everything here.. http://www.pmptrend.com/index.php/en/forum/11-Questions-Answers-Queries-Infos-Etc/88-CPM-Sample-Question#88