Question on Negative Risk

Need help on below question. I know the answer to the question will be either A(if it has been identified Risk) or C (if has not been identified) .But how to decide in this case.


When a negative risk occurs in a project, a response to it would be called:




  1. Add a note hereA contingency plan



  2. Add a note hereFailure planning



  3. Add a note hereA workaround



  4. Add a note hereBackup planning