Question on Cost Variance
Submitted by kiranu23 on Mon, 08/09/2010 - 04:31
You are managing a project with total budget of $ 36,000 to be finished in 1 year . You are in the end of 6th month and currently project is on schedule; however the actual cost of the project is $20,000. What is the cost variance in the project?
A. + $2000
B. - $2000
C. +$16,000
D. -$ 6,000
Can anyone solve this and provide explaination please.
Forums:
pkukilla
Mon, 08/09/2010 - 05:28
Permalink
BAC = 36.000 ( for 1 yr)PV
BAC = 36.000 ( for 1 yr)
PV =(36000/12)*6=18000
In the question its written the project is on schedule so SV=0 (PV-EV=0)
PV-EV=0 --> PV =EV
Cost Variance CV=EV-AC = -2000
kiranu23
Mon, 08/09/2010 - 05:31
Permalink
Thanks a lot...
Thanks a lot...
pkukilla
Mon, 08/09/2010 - 05:34
Permalink
you are welcome.. Please can
you are welcome.. Please can you tell the source of that question