Question on Baseline

Historical data maybe lost when you rebaseline the schedule ...


Is the above statement correct ...as per PMBOK guide pag 99 ...


 


"Changes to the baselines should only show the changes from the current time forward . Past perf may not be changed .This protects integrity of the baselines and the historical data of past performance . 


 


 

Cumulative past data will be impacted on rebaselining in any point of time.


Whole S-curve will get change of EV AC PV.


and hence variance SV CV will also change of any past point of record.


This is called updating of palnning.


Regards


 

Dear Pawar,


I think the statement "Historical data may be lost if schedule is re-baseline ..." is False.


Even as you say about EVM parameters, EVM parameters are calculated for each reporting period. So for example, Reporting period one, lets say CPI was 0.9 and our forecast shows that EAC has not changed.


Suppose during reporting period two, if my EAC changes due to re-baseline of project constraints (like decreasing the schedule might have increased cost for resources), I would have to manage the indices based on current change. How would it change the Reporting period one CPI of 0.9. And also for the fact, whether there is re-baseline or not, EVM parameters are subjected to change in each reporting period based on project dynamics.


Request you to please clarfiy this.


Regards,


Anand KL, PMP


   

PROGRESS
IN TERMS
OF EV,AC,PV

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

   

 

                                             

 

                                     

 

 

 

                                             

 

                                     

 

 

 

                                             

 


this part will be taken as revised baseline
-Yellow Blocks

 

 

 

                                             

 

 

 

As per P99 after rebaselining this part
will remain as original base line yellow blocks

 

 

 

 
     

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 
     

 

 

                     

 

 

 

 

 

 

                                             

 

 

 

 

                     

 

 

     

 

 

 

                                             

 

 

                     

 

 

         

 

 

 

                                         

 

 

 

                   

 

 

             

 

 

 

                                     

 

 

   

 

               

 

 

   

Rebaselining

 

 

 

 

             

Original Baseline

   

 

       

 

           

 

 

 

 

 

 

 

 

 

 

               

 

         

 

       

 

 

           

IN THICK
 BLOCK

 

 

 

 

                               

 

           

 

   

 

 

                 

 

 

 

                             

 

               

 

 

                     

 

 

 

                           

 

             

 


 

   

ACTUAL PROGRESS
IN RED BLOCKS

   

 

 

 

                         

 

           

 

 

   

 

 

               

 

 

 

                       

 

         

 

 

     

 

                   

 

 

 

                     

 

       

 

 


 

       

 

                   

 

 

 

                   

 

       

 

 

 

         

 

                   

 

 

 

                 

 

       

 

 

 

           

 

 

PMBOK P99 HENCE
SPECIFIEING TO MAINTAIN THE PREVIOUS STATUS(baseline, past of that revision point of time) AS IT IS and after that point of time new baseline will be followed- yellow blocks

 

 

 

               

 

       

 

 

 

             

 

   

 

             

 

       

 


 


 

               

 

   

 

           

 

     

 

 


 

                   

 

   

 

         

 

   

 

 


 

                       

 

   

 

       

 

   

 


 

                           

 

   

 

     

 

 

 

 

                               

 

   

 

   

 


 

 

                           

a point
of time >

   

 

 

 


 

 

                                 

 

 


 

 

                                   

 


 

 

                                   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

 


 

 

TIME

 
 
 

 

Hi Vivek,

I dont think if you have understood the posts in reply to your question, i think the more you became complicated :)

Let me answer your question and explain:

Since you refer to PMBOK Guide 4th Edition p.99, the explanation there if you just read and understand it is clear. The PMBOK does not say that statement - 'historical data maybe lost when you re-baseline the schedule... It is probably your own understanding or statement. Hence, i would say, that statement your wrote is not correct.

What PMBOK tells us is that - if we impose changes to the baselines (which means revision to the baseline), should only show the changes from the current time forward.

Let me give you these points.

'Rebaseline' is not an acceptable term in PMBOK and in project management. There is no such thing as 'rebaselining.' The correct term must be 'revision' of the baseline which means, you will change the baseline from the time the need to change or in effect of the approved change requests and forward. This is the ideal thing to do as the PMBOK says, with which I agree.

On the other hand, if you re-baseline your baseline - then this connotes that you will destroy your historical data making that term and even that action not acceptable. Follow me if you want more explanations.

 

 http://www.pmstudy.com/guides2.asp

8 Re-baselining Process of changing the schedule baseline. It is done when schedule delays are very severe, and the project schedule has to be completely changed.

 it is also pmbok term see p 56(pdf87) of pmbok4

--During project execution, results may require planning updates and re-baselining.