Question #8

Your team is completing an exercise to determine which risks have the greatest potential impact on your project. They are assessing the extent to which the uncertainly of each element of the project effects the risk being examined when all other uncertain elements are held at static baseline values. What is this technique commonly known as?

A. Sensitivity analysis

B. Expected monetary value analysis

C. Tonrnado Diagram

D. Modeling and simulation

admin's picture

Probably tornado diagram  PMBOK Guide Fifth Edition (2013) page 338

Sensitivity analysis...thats the definition thr.... but tornado is another name for sensitivity...

So why do u hv both here ....also i notice an error in spell of tornado....so may be thats why we can exclude tht and choose A.