Question #3

 

Risks may be identified during the entire lifecycle of a project.  Identify risk is what type of process?

A. Effort driven

B. Iterative

C. Never ending

D. Qualitative

 

The output of the Perforam Quantitiative Risk Analysis is risk register updates.  What process uses this as an input?

A. Project Integration Management

B. Identify risk

C. Project Time Management

D. Plan Risk Reponses

B. Iterative ( you keep identifying new risks...thru out the project...at times you might know some risk right at the start...and u put them in the proj charter....during control risk...one of the things you do is keep an eye on any new risk....so its not one time....any way rest of the options on their own dont fit the answer)

D. Plan risk responses - you do this based on those updates in risk register---- you update priority based on quantitative analysis....

 

Option B