A project team collects project work performance data and transforms that into work performance information for the key project stakeholders on a monthly basis. Which of the following does not provide a good platform to share this information with the stakeholders?
A. Project file updates
B. Project update meetings
C. Information management system
D. Status review meetings
Forums:


phillipscis
Tue, 11/18/2014 - 17:55
Permalink
A. Project file updates
Project file updates is not a platform of presentation.
ulikkg
Wed, 11/19/2014 - 12:20
Permalink
What is correct answer? I
What is correct answer? I though B. Is Project Update Meetings correct term?
dipti1pmp
Thu, 11/20/2014 - 05:41
Permalink
its proj file updates
prj file updates