Question #1

 

During project execution, an unifentified risk even occurs, catching the team by surprise.  Now that is has ccorred, you must act.  What is your response action?

 

A. Create workload

B. Request guidance from hyour project sponsor

C. Make an appropriate change to the new risk register

D. Transfer the risk as soon as possible

C and D does not seem right.

I have not heard what a workload is - I feel that it could be a typo for workaround. If it were Create Workaround, that is the right answer. Else, I might say Option B (which does not seem that much right to me because you go to the sponsor only after you have exhausted your options). 

admin's picture

Is it really workload ?... what does that mean "?.

 

If risk has occured check for workaround