Quality Mgmt question

Jackie Chan is serving on a project team to help the project manager implement the Quality Management Plan. His experience in Kaizen techniques is a strong asset in this project, which has a heavy emphasis on product-delivery. Which of the following would Jackie Chan find FALSE?


A.  The project's quality audits will assure that the project products fall within the sponsor's acceptance limits.
B.  The process improvement plan will help find waste and non-value added activities in the production process.
C.  Ishikawa diagramming should be included in process analysis to identify underlying problem causes and help create preventive actions for similar problems.
D.  Approved change requests must be analyzed for their impacts on QA audits and quality reviews.

 

Please also briefly explain.

 

Thank you all.

It Seems wordy Q. It speak about Kizan. importance of Chan. but question is which of the following is false.


A.  The project's quality audits will assure that the project products fall within the sponsor's acceptance limits. --->Quality audit qill audit with project plan and process improvement plan.


B.  The process improvement plan will help find waste and non-value added activities in the production process.--> True
C.  Ishikawa diagramming should be included in process analysis to identify underlying problem causes and help create preventive actions for similar problems.--True
D.  Approved change requests must be analyzed for their impacts on QA audits and quality reviews --> True

Sorry i mean ti say

* --->Quality audit will audit with project management plan (Quality management plan and process improvement plan)