Q from simpli learn
Submitted by arindamm on Tue, 10/04/2011 - 03:14
| Question: A project manager is in the process of analyzing activity sequences, durations, resources requirements, and schedule constraints to create an approved project schedule. What should he do NEXT? |
| Options: |
| A. Determine Resource Requirement for each activity in the project |
| B. Use techniques like Critical Path method, What-if Analysis to calculate optimum duration of the project |
| C. Use this approved schedule duration as a baseline and start tracking the project |
| D. Create a Network diagram of the project using one of the diagramming methods |
Forums:


admin
Tue, 10/04/2011 - 04:20
Permalink
Question is not clear.. but
Question is not clear.. but answer should be B
C.. After schedule is done there are other activies we cant directly start tracking the project.