Q on Opportunity
Hi, Please can somebody help on below question:
Q: The project manager for a construction project discovers that the local city council will vote on a zoning change that would open up a new neighborhood to commercial building. She contacts other construction companies in the area that would benefit from the change to ask them to attend the council meeting in order to convince the city council to vote for the change. A “Yes” vote will benefit all of the companies. This is an example of which risk response strategy?
Options:
A. Mitigate
B. share
C. Exploit
D. Enhance


PKMeiyappan.PMP...
Sat, 12/01/2012 - 10:11
Permalink
Q on Opportunity
Answer - D - Enhance. Its what increasing the probability of the opportunity.
mpavas
Mon, 12/03/2012 - 01:40
Permalink
My vote also on D.