project scope planning process

During the project scope planning process, the work breakdown structure should be developed to:

a.      The sub-project level

b.      The level determined by the project office

c.      A Level allowing for adequate estimates

d.      The cost center level

 

The question talks about scope planning process (not define or create WBS). Wouldn't it be choice B in this case?