Project funding and forecasting clarification
Submitted by nbk on Thu, 07/14/2011 - 01:03
Please share your thoughts on these
A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000?
1.Cost Variance
2.Management Overhead
3.Management Contingency Reserve
4.Schedule Variance
Answer 3, What is the assumption here ?
What is the BEST way to make an accurate forecasting of ETC?
1.Manual Forecasting of cost of remaining work.
2.BAC – EV
3.(BAC – EV)/CPI
4.EAC - AC
Answer 1. My choice was 4 ,
Forums:


rahultoraskar
Thu, 07/14/2011 - 05:28
Permalink
Hi nbk,
I'd like to take 2nd question first. Following are my thoughts.
I agree with the answer 1 because the question asks for 'BEST' way to make accurate ETC.
Option 1 talks about bottom-up approach where you sum up cost of the all remaining work which will tell you accurate ETC.
My thoughts on question 1:
Answer 3 is correct because the management contingency reserve is planned for unknown unknown which is on top of the budget (which involves known unknowns).
Hence, option 3 is more appropriate.
Dernamasa Greta (not verified)
Tue, 11/06/2012 - 11:13
Permalink
The emphasis will be on
The emphasis will be on transportation project management, because this is where the first instance of reference class forecasting occurred. government-grant grants for college