PROJECT CLOSURE and CHANGE MANAGEMENT STEPS
Submitted by parweztarafdar on Tue, 07/02/2013 - 09:17
Hello,
Can spme one please confirm my undersatnding on Close project and changemanagement procss holds good. I am confused mostly on the bpth topics after giving some mock tests.
Change management
- Prevent unnecessary changes
- identify them early
- Document CR
- Asses the impact (triple constarint plus quality)
- create options (crashing fast tracking etc)
- Input to Change management system(CCB,procedures tools etc)
- Update the baselines and other documents
- inform stake holders
Project closure
- Verify the project scope work
- close procurment
- Client acceptance
- Final performance report
- LL
- Archive Project document
- hand off of completed work
- Relase resources
Please guide me if there is a GAP in the knowledge
Thanks
Parwez
Forums:


bridge
Tue, 07/02/2013 - 18:26
Permalink
Have a look at this
Have a look at this -
http://pmzilla.com/sequence-procurement-closure