Procurement Question
Submitted by pmpcracker on Fri, 05/10/2013 - 02:42
A procurement contract will include terms and conditions, and may incorporate other items that the buyer specifies to establish what the seller is to perform or provide. In this context who is responsible to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies
A. Procurement manager
B. Project manager
C. Project Managerment Team
D. Project Team
Forums:


crushPMP
Fri, 05/10/2013 - 03:13
Permalink
A. Procurement Manager?
A. Procurement Manager?
pmpcracker
Fri, 05/10/2013 - 03:30
Permalink
Answer -C
Answer -C
bridge
Wed, 05/15/2013 - 11:32
Permalink
Why the Project Management
Why the Project Management Team ?
For project mangement team also, the project manager is responsibile.
So the answer should be project manager.
Can you explain your answer ?
rwmv
Fri, 05/10/2013 - 11:01
Permalink
B
Project manager -----coz the question says adhereing to procurement policies throughout the project.
bkthakkar
Wed, 05/15/2013 - 16:02
Permalink
Project Manager in the one
Project Manager in the one who sits with the Procurment Manager in clarifying the scope and making understand the bidders in regard to the project.deliverables. Therefore the answer should be Project Manager
motivation
Thu, 05/16/2013 - 04:53
Permalink
Answer is A
Answer is A.
The procurement dept. looks after all legal and policies related affairs when it comes to procurement contracts. The project manager needs to know about these policies but the penultimate responsibility is shouldered by procurement manager.
What's the answer of the Q. in the source?
sspawar
Thu, 05/16/2013 - 05:48
Permalink
In my opinionA -- certainly
In my opinion
A -- certainly not be the answer. procurement manager , is made up /nonpmbok term. Also it is not necessary, all projects should have seperate procurement cell/ office. It may also be possible that one PM can be served by many Procurement Administrators.
B -- here question is asking about - who is responsible to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies.
here accountability will be of PM but responsibility will be of whole PR MGT Team--- all procurements means all contracts, it involves - all project requirements, scope, planning, execution, monitoring and closing all. It is not like to be dealt award of a contract or a purchase an item, or making a payment.
C - as above stated in B
D - Project team members other than proj Magt team, are only responsible for their specific work.
rwmv
Thu, 05/16/2013 - 06:03
Permalink
Project manager
Project Manager is responsible to ensure that all procurements meet the specific needs of the project while adhering to organizational procurement policies
cnppmp
Thu, 05/16/2013 - 08:29
Permalink
Project manager
This is talking about the project scope, which is managed and provided to procurement manager by project manager, looking at the main context of this question "In this context who is responsible to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies" Tricky thing what is being asked.
will be interested to see the right answer.
Regards
CN Patil
Novjot
Thu, 05/16/2013 - 09:58
Permalink
Project Manager
B project manager . Question is talking "who is responsible to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies" . Its specific needs of the project which is Project Manager responsibility.
th9063
Fri, 07/05/2013 - 09:02
Permalink
PMBOK Page 315 2nd paragraph
PMBOK Page 315 2nd paragraph 2nd sentence
Answer C