You are about to contract out a project to a service provider. However at the time of awarding the contract, you are not sure of the total effort involved. Which of the following would best suit your purpose?
-
Cost-Plus-Fixed-Fee (CPFF)
-
Time & Material (T&M)
-
Fixed Price (FP)
-
Cost-Plus-Incentive-Fee (CPIF)


crushPMP
Fri, 05/17/2013 - 14:27
Permalink
Had I got this question in
Had I got this question in the exam - I would have gone with B. But since this made it up her on the forum - I'll have to go with D :-)
BK
Fri, 05/17/2013 - 14:56
Permalink
B is given as right ans.
B is given as right ans.
BK
Sat, 05/18/2013 - 09:10
Permalink
Crush, pls share the link of
Crush, pls share the link of discussion. Thanks
eng_mut
Fri, 05/17/2013 - 15:23
Permalink
service provider , i think B
service provider , i think B
rwmv
Sat, 05/18/2013 - 09:35
Permalink
B
B