 As part of Close Procurement process, the project manager prepares a complete set of indexed contract documentation, including the closed contract, to include with the final project files. This is called a:

A. Procurement File

B. Documentation File

C. Closure Report

D. Closure File

 I guess, it is B.

 Procurement file -

OPA updates of Close procurement process..pmbok pg 344

crushPMP's picture

^ Yes, Correct ans is A