Process Groups overlap question

While the five process groups are typically completed in order, they often overlap with each other throughout the project. Which two process groups should never overlap unless a project is canceled?

A. Initiating and Closing

B. Initiating and Executing

C. Initiating and Monitoring and Control

D.Planning and Closing

 

What is your choice and why?

Thanks

Jai
 

A

fig 3-2

 OPTION A

crushPMP's picture

Definitely A

Yes, Its A. I came across this question and felt intresting so wanted to share it with others.

Thanks Pawar and CrushPMP