PMP Some Confusing Topics / Questions

 Please help me in understanding these

1.  If the Questions ask about THREE POINT ESTIMATE , which formule should I choose, as in one of the mock test, I used (O + 4M + P)/6 , but the answer was (P + M + O)/3, though it was not mentioned that its a triangular distribution

2. How to differentiate between Risk Exploit and Risk Enhancement , any examle would be great 

3.  Risk Mitigation & Risk Acceptence  -- I understand we need to have contigency reserve  to accept risk , but in some mock test, some action has been taken for the accepted  risk. This confuses me as to how to differntiate between Risk Mitigation and Risk Accepetence.

4. If senior Mgmt ask,  whether  the project will meet the expected budget, which EVM  value will you share.

Answer was TCPI  and I thought it was CPI. 

 

A.

 weighted  average or beta distribution  fotmula 

 (O + 4M + P)/6 = expected value

THREE POINT ESTIMATE / triangular dist formula 


(P + M + O)/3
(fig 11.4)
 
B.
refer
 
C.
acceptance are of 2 types 
active --- uses contingency reserve 
 
and
 
passive --- nothing to do 
Read PMBOK - p304, 
 
D.
Cost performance Index is general term, 
see TCPI is also a CPI.
but when you are asked , about expected budget, means it is asked for the future remained project.
hence conerned factor will be cpi of remained work = TCPI.
-----
I think you should study and learn more.

thanks pawar ji,  Yes I need to learn more.