Q. Jack and his team have identified 200 risks and 10 major causes of those risks. However, during project planning, the team is unable to reduce an effective way to mitigate or insure against a particular risk. It is not that kind of work that can be outsourced, nor can it be deleted. What should be the best approach?
A.Try to find different ways to mitigate the risk
B. Accept
C. Avoid
D. Transfer
What Should be Correct Answer-
Check Answer and Source= Click Here
For PMP Exam Questions on a PMP Exam Simulator