PMP question
Submitted by Itmaster1979 on Sat, 11/17/2012 - 13:16
| uestion: Which of the following activities most deserves your immediate attention? |
| Options: |
| A. AC=3000 EV=2900 |
| B. PV=3000 EV=2900 |
| C. AC=3000 EV=3200 |
| D. EV=3000 AC=2400 |
can someone explain please


ilasubbu
Sat, 11/17/2012 - 14:58
Permalink
Answer is D
Hi,
In principle, schedule or cost anything has more variation than planned should be given attention at first. PMP advises to calculate schedule or cost always accurate and not most favourable / infavourable to project.
In this case,
A. CPI = 0.97
B. SPI = 0.97
C. CPI = 1.07
D. CPI = 1.25
means, the variation in D is more compared to others, so the attention to be paid on Case - "D".
Itmaster1979
Sat, 11/17/2012 - 17:59
Permalink
Thanks a lot, my exam is on
Thanks a lot, my exam is on Monday 19/11/2012, any advise