PMP question

uestion: Which of the following activities most deserves your immediate attention?
 
Options:
A. AC=3000 EV=2900
B. PV=3000 EV=2900
C. AC=3000 EV=3200
D. EV=3000 AC=2400

can someone explain please

Hi,

In principle, schedule or cost anything has more variation than planned should be given attention at first. PMP advises to calculate schedule or cost always accurate and not most favourable / infavourable to project.

In this case,

A. CPI = 0.97
B. SPI = 0.97
C. CPI = 1.07
D. CPI = 1.25

means, the variation in D is more compared to others, so the attention to be paid on Case - "D".

 

 Thanks a lot, my exam is on Monday 19/11/2012, any advise