PMP question
Submitted by munishmsh on Tue, 07/26/2011 - 09:54
Which of the following contracts has the most risk for the buyer?
a. Cost plus fixed fee(cpff)
b. Time and Material (T&M)
c. Cost plus award fee (cpaf)
d. Fixed price (FP)
Would you please explain. It should be Cost Reimburable
Regards
Msh
Forums:


yashbindlish
Tue, 07/26/2011 - 15:26
Permalink
Answer is: B Time and
Answer is: B Time and Material (T&M)
munishmsh
Tue, 07/26/2011 - 16:51
Permalink
thanks....Can I have the
thanks....Can I have the explaination too...
bschand
Tue, 07/26/2011 - 17:28
Permalink
T&M - uncontrollable by buyer
T&M contracts - Material and human resource cost incurred to do work will be buyer's responsible. If work takes more time than planned it will be more cost for Buyer; Seller enjoys cost benefit here;
Fixed Price & its flavours contracts - Buyer and Seller accept for fixed fee to get work done; If work takes more time than planned it would not cost anything much for Buyer; Seller faces problems here.
Hope this clears your doubt.
Thanks,
Chandrasekaran
aaron
Thu, 07/28/2011 - 13:50
Permalink
Answer should be A (Cost
Answer should be A (Cost Reimbursible + Fixed Fee)
CR contracts always carry higher risk (for buyer) than T&M contracts.
CRPP carries highest risk followed by CRFF and then CRAF
sili18
Thu, 07/28/2011 - 21:47
Permalink
I Agree with you Aaron. The
I Agree with you Aaron. The Answer should be A (CPFF)