PMP certification practice questions
Hi,
I have come across followin question
You have been recently hired to be a project manager at a bio-tech company to develop a new drug to treat pancreatic cancer. This project requires significant coordination across multiple departments, from R&D to Manufacturing.
You've attempt to gain the cooperation of the Chief Scientist (who reports to the V.P. of R&D) within the R&D department. You need her assistance to answer some questions regarding the clinical testing process of this new drug.
However, the Chief Scientist is un-interested in your project and provides little or no feedback to your questions. Since your project is NOT one of her priorities, she's been rather unresponsive to your questions.
What should you do in this situation?
D) Negotiate with the VP of R&D to establish expectations of the Chief Scientist and request to participate in the Chief Scientist's annual performance review.
-
[Ans: D]
- Many projects require team members from various departments in the organization to work together on different aspects of the project. Unfortunately, resources can be scarce when multiple projects are competing for the same resources. In such cases, team members will likely remain loyal to their supervisor / functional manager. Since the functional supervisor often writes the performance reviews, team members will often have greater loyalty to the functional supervisor than to the project manager. In order to remedy this, the project manager can negotiate with the functional supervisor in contributing to the employee's performance review.
To say the least, it takes skillful, diplomatic abilities to navigate through the organizational politics. Although project managers have little authority in functional organizations, with the right knowledge, they can succeed at their projects.
I doubt about answer D . According to me Ans C is more correct. Can anybody explain why D is more correct than C


admin
Fri, 11/20/2009 - 08:33
Permalink
Ans C is not correct, since
Ans C is not correct, since you do not have any control over the Chief scientist. The only thing you can do is take help from his manager to get him involved. So only A and D can apply. Even if you use Option C, Chief scientist will not move from his position, since he will have many other projects to look after and he can easily justify why he is not supporting your project.
Depending upon the context even A could be correct answer. but in D you are getting some control by perticipating in the appraisal of Chief scientist and its more like to get his continued cooperation if you choose D