Can anyone suggest easiest way to calculate the FLOAT on activities??

Please advise.

 

Thanks

 

 

 First Calculate the critical path

then calculate the longest path containing the activity for which float needs to be measured

and then just follow this: float= (critical path value/duration - longest path value/duration).

 

BK 

conceptually you are  correct.

for clarity

I want permission to make a little change, 

First Calculate the critical path

Then calculate the longest path other than critical path (second longest)  for calculating minimum possible Float (Total Float).

Then just follow this: 

Float (Total Float)= [Total Duration of project (at critical path)  - Duration at longest path other than critical path].