I am working with PMI online application to submit for qualification evaluation. Got question on 4500 Hrs project management experience. Following are rough calculations i came up with:


 

Approximate effort spent on these PM Domains

 

#


Project Name


Title


Start Date


End Date

 

Total Hours


Initiating %


Planning %


Executing %


Monitoring & Controlling %


Closing %


Total %


1


Proj 1


Proj Lead


x


x

 

706


13%


20%


45%


12%


10%


100%


2


Proj 2


Proj Lead


x


x

 

1337


15%


20%


30%


25%


10%


100%


3


Proj 3


Proj Lead


x


x

 

2057


5%


20%


50%


20%


5%


100%


4


Proj 4


Proj Lead


x


x

 

1353


15%


15%


50%


15%


5%


100%


 


Totals 


 


5453


48%


75%


175%


72%


30%


 

 

 

I am getting required hours. But in every process must i have accumlated more than 100% ?

Initiation - 48% ; Planning 75% ; Executing 175%, Mon & Control 72% and closing 30%

Does the my job title okay for it ?

 

admin's picture

Job title is not important. If audited you should be able to get a letter from your manager or you company attesting that you have spent these hours on PM activities

Does the hours looks good ? % of each process contribution ?

admin's picture

As long as you have valid 4500 hours, distribution is not important.