PM Study critical path question
Question No : 129 |
||
![]() What is the status of the project? |
||
Choice 1 | Behind schedule, under budget | |
Choice 2 | Ahead of schedule, under budget | |
Choice 3 | Ahead of schedule, over budget | |
Choice 4 | Behind schedule, over budget |
Earned value (EV)
= The sum of the approved cost estimates for activities completed during a given period
= Estimated cost of work that is completed after day 11
= $ 5,000 + $ 5,000 + $5,000*.50 = $ 12,500 (because Task A, Task B are complete, Task C is 50% complete)
Present value(PV)
= Present work to be completed after day 11
= $ 5,000 + $ 5,000 + $ 5,000 * (1/5) (because at end of day 11, according to our plan, Task A, Task B should be complete; Task C only one day out of 5 days should be complete, i.e., 20% complete ($ 1,000 of work should be done)
= $ 11,000.
Actual cost (AC)
= Actual Cost of work completed
= $ 13,000.
Schedule variance (SV)
= EV - PV = $ 12,500 - $ 11,000 = $ 1,500
Since SV is positive, we are ahead of schedule.
Cost variance (CV)
= EV - AC = $ 12,500 - $ 13,000 = - $ 500
Since CV is negative, we are over budget.
would you please help me to with this question
i just want to know why he used CV & SV instead of CPI & SPI
when we can use variance and when we can use index ?
sanskrit
Sat, 05/25/2013 - 12:14
Permalink
In this question it does not matter
You can use either CV & SV OR CPI & SPI, You will get the same result
cnppmp
Sat, 05/25/2013 - 13:29
Permalink
C
C
Regrads
CN Patil
vijayavadrevu
Sat, 05/25/2013 - 17:43
Permalink
Even with CPI and
Even with CPI and SPI,
CPI=EV/AC = 0.9615 and SPI = EV/PV = 1.136
Hence it is ahead of schedule and over budget
arianaseri
Mon, 08/15/2016 - 07:08
Permalink
exactly correct
exactly correct