Please help to explain this question
Submitted by munishmsh on Wed, 07/13/2011 - 08:25
You just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:
Which potential inconsistency in the diagram should you solve right now? | ||
| Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence. | ||
| Activity F is open ended in relation to the path divergence after the start milestone. | ||
| You cannot calculate a critical path when lags and/or leads are calculated in percent. | ||
| Activities E to F need another task drawn as a hammock to calculate Level Of Effort. | ||
Forums:



rahultoraskar
Thu, 07/14/2011 - 05:36
Permalink
Hi munishmsh,
Per my understanding, option 3 appears to be correct answer.
Reason is that if the lag / lead are in percentages then it will be difficult to calculate the critical and near-critical paths.
I believe this inconsistency in the diagram should be solved first.
gabrielroj
Sat, 11/05/2011 - 23:01
Permalink
Network Diagram http://www.oliverlehmann.com question
The answer according to http://www.oliverlehmann.com is:
Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence.