You are a project manager at a construction company. You have to plan when to obtain the products and services from the vendors. In which of the following process this should be determined?
Answers :  
 A)Estimate Activity cost
 B)Plan Procurements
 C)Define Scope
 D)Define activities

Ans is C.

Please provide clarification . I am thinking that option B is correct.

You are correct. The correct answer is B

 

The Plan procurement process involves determining wheather to acquire outside support, if so how to aquire it, how much is needed and when to aquire it. PMBOK Page No 317