PERT on Critical path question
Does anyone know how to calculate the below.
Question:
Together with your team you applied three point estimation on a Critical path containing two activities.
The following duration uncertainities are calculated using +/-3sigma confidence interval.
The duration uncertaining-defined as Pessimistic minus optimistic estimate - of the first activity is 18 days; the second estimate has an uncertainity of 24 days. Applying the PERT formula for paths, what is the duration uncertaining of the entire path?
A. 21 days
B 30 days
C 42 days
D No statement is possible from information given.
Answer is B.


apmeena
Thu, 08/25/2011 - 10:41
Permalink
PERT on Critical path question
Can anyone help on the above calculation?
apmeena
Thu, 08/25/2011 - 12:35
Permalink
I found it finally. For the
I found it finally.
For the benefit of all :
The first activity has a sigma of 3 days (18/6), the second activity has a sigma of 4 days (24/6), so combining them the overall sigma is 5 days (SQROOT (3squared + 4 squared)). Therefore 6 sigma of the combination is 30 days (ie 6*5days).
Aditya Mishra
Sat, 08/27/2011 - 23:00
Permalink
I find your calculation a bit
I find your calculation a bit strange. From what I have studied from Rita ( I am yet to take my test on 30th), it should be done like below;
Uncertainity for Activity A = Standard Deviation = 18
Variance for ACtivity A = 18*18 = 324
Uncertainity for Activity B = Standard Deviation = 24
Variance for ACtivity B = 24*24 = 576
Total Variance for all activities on CP = 324+576 = 900
SD (Uncertainity) for the entire path = Square Root(900) = 30.
Can you tell me where did you get the formula for sigma calculation.
Adi
fatraif
Sat, 03/24/2012 - 15:22
Permalink
I guess the other answer/method is more realistic
http://www.youtube.com/watch?v=vW6CAbP43cI
after calculating the 5 with +/- 3SD which means 3x5 on right of ya xis of the bill shape diagram and 3x5 on the left side will give 6x5 or 15+15 == 30