PDN - Precedence Diagramming Method

Question


Is PDM - Precedence Diagramming Method


1. Finish to Finish relationship


2. Finish to Start relationship


I have been seeing conflicting answers for this questions.


Thanks

cnppmp's picture

PDM has four dependencies FS, FF, SF and SS in AON network diagram but most commonly used is Finish to Start relationship

 

May be your question asked is incmplete or not properly phrased I guess.

Regards

CN Patil

 yes, i think the question is incomplete. Not enough info to determine whether it is SF or FF