Hello,
i am reading Rita's book to prepare my PMP. In the "Perform qualitative risks Analysis" process, it is said "Qualitative risk analysis" can lead to a number to be used to rank the project in comparison to other projects". The question i had is how to obtain this number from individual risk score ?
Is this number used to rank the project in comparison to the other is the higher score of all risks identified during "Qualitative risk analysis" ?
Thanks
Forums:


admin
Mon, 09/08/2014 - 04:12
Permalink
Yes from overall risk score
Yes from overall risk score of the project, you should be able to compare with other projects. Once you have quantified the risk, each project will have a risk exposure and overall risk exposure can be calculated.
All this is done through software algorithms.