 You are managing a complex project which requires some highly skilled resources on embedded design. You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you need to free these resources for reassignment. You are working in which kind of organization structure?

A)Functional

B)Projectized

C)Matrix

D)Tight Matrix 

crushPMP's picture

C?

 You are right? Why not Projectized?

crushPMP's picture

I would say, I was split-even between B and C and eventually decide to go with C.


The situation describes the mix of both Projectized (You are managing a complex project ) and Functional (You obtain these resources from the organization pool. You specify the duration for which they would be required. Once your project activity is complete, you need to free these resources for reassignment)

 Thank You for the explanation

 The keyword for me was the Free the RESOURCES for REASSIGNMENT. Its definitely not projectized nor function- coz in functional they work their day work and the project. so its Matrix.