Opportunity cost question and answer

support@mypmpexamprep.com's picture

 Project A has an IRR of 12% and an NPV of $100,000 for a 2 year

duration. Project B has an IRR of 16% and an NPV of $118,000 for a 4 year
duration. What is the opportunity cost, if you select project A instead of project B?
A.) -100,000
B.) 118,000
C.) 100,000
D.) 109,000
 
Answer is : B
When selecting between two options (or projects) then the opportunity cost is simply the value of the option (or project) that was not selected. In this case, we
selected project A over project B. This means that our opportunity cost = the value of project B = $118,000. The IRR and duration of the projects are irrelevant.
 
Thanks,
RP, PMP