Oliver Lehmann ( 75 ) study question number 16
Hi. can someone walk through Oliver Lehmann study question number 16? The answer is listed as d but I am not sure how this caluculated. Thanks..
http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm
You are running a project for a customer based on a cost reimbursable contract with the following terms:
Target costs: $ 1,000,000
Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000
Which is the PTA (= Point of total assumption, Break point) of the project?
a. $1,300,000
b. $1,500,000
c. $80,000
d. $1,125,000


swet
Mon, 06/14/2010 - 13:34
Permalink
Ceiling Price =
Ceiling Price = $1,200,000
Target Price = $1,000,000 (Cost) + $ 100,000 (fee) = $1,100,000
Target Cost = $1,000,000
Buyer Share Ratio = 0.8 (80%)
PTA = [ Ceiling price - Target price ] / Buyer's Share ratio + Target Cost
= [$1,200,000 - $1,100,000] / 0.8 + $1,000,000
= $1,125,000
= Option D
Swetketu Patel, PMP
dhirajbisht
Fri, 02/18/2011 - 10:43
Permalink
Oliver Lehman 175 Question Sample Paper . Question no 34
A project has the following
Earned value data assessed: AC: $ 4,000,000 CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000What is the
Earned value of the project? 34o $3,000,000
o $3,500,000
o $4,480,000
o $5,650,000
Can some one pls make me understand if this question is wrong ?
Cost variance is -500000 and CV = EV - AC So if we go as per that it should be EV = CV + AC and if we apply same thing here answer should not be 300000$ & as per Oliver Lehman answer sheet teh answer is 300000$
Can some one pls explain
sv
Mon, 02/28/2011 - 21:54
Permalink
Oliver Lehman 175 Question Sample Paper . Question no 34
as per oliver lehmann ans sheet the ans is 350000 (the same that u got).
SV
jmoore0536
Tue, 07/12/2011 - 20:18
Permalink
Is it me or is that Math
Is it me or is that Math wrong?
mohankinra
Thu, 07/14/2011 - 05:02
Permalink
The answer should be 3,500,000
CV=EV-AC
EV=CV+AC = -500K+4000K=3500K = 3,500,000
Regards