Numericals

 

Consider the information below providing cumulative data for the first four months of a twelve-month project. Assuming the project continues its progress at about the same rate, the total project duration at completion will be approximately:

Month

PV

EV

AC

1

10

10

11

2

20

19.5

20.5

3

35

33

34.5

4

50

44

45

Choose one answer.

 
    a. 13.6 months           
    b. 10.2 months           
    c. 12.8 months           
    d. 8.4 months          
 

answer is A

2)

In preparing for a team meeting you want to let the team know how they are doing on the project schedule overall. You calculate the task achievements as follows: Planning has a PV of $20,000 and an EV of $25,000, Testing has a PV of $17,000 and an EV of $15,000, and Design has a PV of $34,000 and an EV of $42,000. As a whole your project is:

a. 15% behind schedule Incorrect

b. 15% ahead of schedule, but over budget Incorrect

c. 15% behind schedule and budget Incorrect

d. 15% ahead of schedule Correct

please show the calculations ...answer is D

3)

WOTS Inc has designed and installed landscaping around Hai’s new house. The estimated cost for the work was $50,000, based on a Cost Plus Fixed Fee contract (CPFF). If the fixed fee was set at 10%, the final cost was $47,000, and Hai’s initial payment was for $20,000, what is the amount of Hai’s final payment to WOTS Inc

Choose one answer.

a. $55,000 Incorrect

 

b. $35,000 Incorrect

 

c. $31,700 Incorrect

 

d. $32,000 Correct

 

 

 

1) I CANT SEEM to figure out the 1st one, post the solution described in the simulator

 

2) PV = 20000 + 17000 + 34000 =  71000

    EV = 25000 + 15000 + 42000 = 82000

 

   SV = 82000 - 71000 = 11000

SV % = (SV/PV) x 100 = (11000/71000) x 100 = 15%

So the answer is d) 15% ahead of schedule

 

3)  I will just give a try for this one, not sure if the approach is right

Target Cost = 50000, Fixed Fee is 10%  of estimated amount = 5000, I took the fee of he original amount because in CPFF, the fee is estimated at the begining as a percentage of the Target cost and will not change if the cost increases or decreases

Actual Cost = 47000.

Advance Payment = 20000

So Final Payment = 47000 + 5000 - 20000 = 32000.

 

 

 I think you are right. for above 2 q.

1st question not tricky but with extra information.

4th month SPI = 0.88

Thus this rate will continue till completion.

88% work will be completed in 12 month

hence 100% will be completed in 12*100/88 = 13.6 months (A)