NPV without discounted cashflow
Absolultely baffled!!! Calling on the PMP Elders to assist!
An upgrade of your company's financial system is estimated to save your department $ 10 000 in the first year, $ 30 000 in the second year and $ 75 000 in the third year. The cost to upgrade the system is $ 150 000 and is expected to take 15 months to implement. Given this data what is the approximate present value (PV) of this project?
A: $ 95 000
B: $ 102 000
C: $ 132 000
D: $ 252 000
Answer is B: Explanation
PV = 10 000 / (1+0.05)1, 30 000 / (1+0.05)2, 75 000 / (1+0.05)3
Now the question is, where do I get the 0.05 from????