shortest amount of time
Submitted by san on Wed, 04/24/2013 - 04:37
You have a project with four tasks as follows: Task 1 can start immediately and has an estimated duration of one. Task 2 can start after task 1 is completed and has an estimated duration of four. Task 3 can start after Task 2 is completed and has an estimated duration of five. Task 4 can start after Task 1 is completed and must be completed when Task 3 is completed. The estimate for Task 4 is ten. What is the shortest amount of time in which the project can be completed?
Answers :
A)10.0
B)9.0
C)18.0
D)11.0
Forums:


sspawar
Wed, 04/24/2013 - 07:41
Permalink
11
11
ssundar
Wed, 04/24/2013 - 08:07
Permalink
how did you calculate pawar?
how did you calculate pawar?
sspawar
Wed, 04/24/2013 - 08:19
Permalink
1 5 5
1
5
5
10
2/4DAYS
>
3/5DAYS
0
1
>
>
1/1DAY
>
1
11
FF+1
>
4/10DAYS
<
san
Wed, 04/24/2013 - 11:13
Permalink
As per this , shortest
As per this , shortest duration could be 10 (1+4+5) =10 (task 1-2-3)
task 1-4 = 1+10 =11
Since question is about shortest duration I opted for 10. Please correct me if my understanding is wrong in analysing this question.
crushPMP
Wed, 04/24/2013 - 13:52
Permalink
D. 11 is the shortest, as
D. 11 is the shortest, as Task 4 has a FF dependency with Task 3
sspawar
Wed, 04/24/2013 - 14:12
Permalink
question is askingwhat is
question is asking
what is the shortest amount of time in which the project can be completed?
it is not asking what is shortest duration path.