Can anyone suggest easiest way to calculate the FLOAT on activities??
Please advise.
Thanks
BK
Sat, 04/13/2013 - 10:05
Permalink
First Calculate the critical path
then calculate the longest path containing the activity for which float needs to be measured
and then just follow this: float= (critical path value/duration - longest path value/duration).
sspawar
Sat, 04/13/2013 - 13:25
conceptually you are correct.
for clarity
I want permission to make a little change,
Then calculate the longest path other than critical path (second longest) for calculating minimum possible Float (Total Float).
Then just follow this:
Float (Total Float)= [Total Duration of project (at critical path) - Duration at longest path other than critical path].
BK
Sat, 04/13/2013 - 10:05
Permalink
see if this helps
First Calculate the critical path
then calculate the longest path containing the activity for which float needs to be measured
and then just follow this: float= (critical path value/duration - longest path value/duration).
sspawar
Sat, 04/13/2013 - 13:25
Permalink
BK conceptually you are
BK
conceptually you are correct.
for clarity
I want permission to make a little change,
First Calculate the critical path
Then calculate the longest path other than critical path (second longest) for calculating minimum possible Float (Total Float).
Then just follow this:
Float (Total Float)= [Total Duration of project (at critical path) - Duration at longest path other than critical path].