PMP- Question on Change request processing sequence ?
Hi,
Q1. From the books and tesks taken, I couldnt come to a conclusion on the change management sequence. This is what I think of. Folks, who has done it as per PMP process, please correct the the step sequence below. I feel it will help many out there.
1. The M&C process shows a variance/a defect is identified/a new request coming from stakeholder
2. PM will analyze the impact of the change along with the team, against 6 project constraints
3. If the change is within PM authority (or CCB not available in org) -> CR is generated, doesnt go to ICC or CCB - >CR will be appoved by PM ->The change will be entered into change log after implementation -> Communicate the change to stakeholders [somehow].
4. If the change is beyond PMs control, will go for CR approval process. as below
5. If the request is from a stakeholder, PM will inform the impacts to the stakeolder -> PM will request them to create a formal CR.
6. The CR goes to the CCB and gets approval/rejection from the board which may include the customer representative.
7. Approved CRs goes to execution process DMPE -> The change will be entered into change log after implementation -> Communicate the change to stakeholders.
------------------------------------------------------------------------------------------------------------
Q2. Step 2, when should change log be updated ? before or after the implentation ?
Q3. Why do we need a CR process also for implementing the changes which are already pre-planned as risk response strategies in the planning process. ? Isnt it an overhead ? Cant PM bypass this as per step 3 ?
Q4. Page 312 PMBOK says Sometimes CR are not needed for implementing contingency plans and work arounds. When this happens, how will the execution process gets the required change input as [the Approved CR ] doesnt comes into picture ?
Q5. If changes doesnt require CR, then will Integrated change control come to picture?. Then how this change will be tracked, how it will be communicated to stakeholders which I belive happens as part of configuration management system in Integ CControl?
Q6. Crucial question is , do we need CR to be there, to make any project/product change, always ?
I want to get this very clear, as it confuses me a lot in answering the questions.Pls help.
Renji


sspawar
Fri, 03/29/2013 - 15:23
Permalink
these may help
these may help you
http://www.pmzilla.com/perform-integrated-change-control-1
http://www.pmzilla.com/change-control-question
http://www.pmzilla.com/scope-change-question-confusion