Sample question of PMPQ

 This is a question included in PMPQ Lite version:

Some companies conduct a post-bidder conference to announce which bidder will receive the contract. Which of the following would also be discussed in these post-bidding conferences?

A) Sharing of each bidders intellectual property with all of the bidders
B) Showing all of the bidders the winning bidders proposal
C) Explaining to each bidder the reason(s) why they were not awarded the contract
D) Discuss future contracts that each seller can consider bidding on
 
To see the answer go to www.pmtraining.es/PMPQeng.htm, try PMPQ Lite, and go to question number 4 of Procurement (Knowledge Areas section).
Regards
admin's picture

Answer would be C

I vote for C. All the other 3 are not valid.

You are right. "C" is the correct.