1 week has 5 days or 7?

A question from rita, 

 
A project has the following risk:
5% probability of an additional acceptance test resulting in 3 weeks delay
50%  probability the next software release will not be ready by the due date resulting in an 8 week delay
30%  probability that a new resource will be available and duration of activity will be reduced by 4 weeks.
 
The answer is 20.65 days, by the below formula
 
(.05 * 21) + (.5 * 56) - (.3 * 28)
 
My question is why 7 days are assumed in a week. I shoudl be 5 days right. I remember it reading it some where that assume 8 hrs a day and 5 days a week in solving numericals
admin's picture

week is generally 7 days. work week can be 5 days. For schedule calculations assume 7 days.  

 Ok, I will take this. Thanks.