RITA's Process Chart
Submitted by PKMeiyappan.PMP... on Wed, 10/24/2012 - 14:25
Hi,
Need Help on Rita's Process Chart. Under the Initiating Group - 2nd Item is "Determine Company Culture and existing systems". I would like to know what exactly meant by "Existing Systems". How it would be different from the next item - "Collect Processes Procedures & Historical Information"?
Thanks in advance.
Regards
PK
Forums:


mkar
Wed, 10/24/2012 - 17:41
Permalink
PMI-ism
Hi:
Read Rita's PMI-ism, 12 & 13, where
Historical Information & Lessons Learned is Organizational Process Assets
Existing Systems & Culture of a company is Enterprise Environmental Factors.
Thanks
sspawar
Fri, 10/26/2012 - 16:42
Permalink
Existing System
Existing System
All external and internal system , that are currently influencing the company working.
These may be like - company's configeration system, information gathering and distributing system, government and indusrial regualations. Environmental and social constraints, etc, which are either affecting the company or company adapting them.