Risk register and project management plan
Submitted by Antoine D on Mon, 10/01/2012 - 22:41
I passed a mock test and one of question was asking if the risk register was a component of the project management plan. The answer was yes, the risk register is one of the component that makes up the project management plan.
I woudl think that the risk register is a project document and is not part of the project managment plan.
What do you think?
Forums:


anand_kl
Wed, 10/03/2012 - 04:33
Permalink
Project Document
Dear Antonie,
You are correct, Risk register is Project documents.
To refer which is part of Project Plan and which is a Project document please refer:
PMBOK Page 350 A.1.2
Otherwise also, in respective Project Document updates you can see, for example in:
PMBOK Page 88
PMBOK Page 141 6.2.3
PMBOK Page 293 - 11.3.3
Hope this helps.
Regards,
Anand KL, PMP