question from FastTrack

 Hi,

 

Just an info on this question that is quite easy but i don't get it.

Which of the following you DON'T need to do if there is a major delay on a NON critical path activity?

a) investigate delay    NOK

b) revaluate which path is critical   NOK

c) change the project schedule  OK

d) review the float time for the activity  NOK

 

I have selected c) since i though i need to reestimate the critical path after some activity time si changed.. wasn't it?

 

 

 

 

 Your choice "C" is correct. this is the thing we "DONT" need to do as asked in the question.