Clarification needed in Verifying a product
Submitted by mohanna81 on Mon, 06/04/2012 - 09:39
- Verifying a product meets the specifications, is part of the closing process group.
It think this should happen in the monitoring and controlling group as part of quality control process
thanks in advance
Forums:


projmanpro
Mon, 06/04/2012 - 09:46
Permalink
From where did you read that
From where did you read that verify product is part of the closing process?
mohanna81
Tue, 06/05/2012 - 05:55
Permalink
From a book called 800 PMP question 2010 edition
PMP Exam Prep Questions, Answers, & Explanations 800 Question 2010 edition
PMNovice
Tue, 06/05/2012 - 00:06
Permalink
Hello,It seems you are
Hello,
It seems you are talking about Verify (product) scope, which happens during Monitoring and control.
Antoine D
Sun, 06/10/2012 - 00:50
Permalink
Quality control process
Quality control process occurs before the verify scope.
Quality control process focuses on the respect of quality standards (e.g. number of defects) as opposed to verify scope that focuses on the respect of acceptance criterias and project objectives.
sspawar
Sun, 06/10/2012 - 04:35
Permalink
Flow Diagram 4.13
Yes it is also a part of close project, as a pre phase of input - accepted deliverables, though it is processed in monitoring and controlling process groups 5.4.
output of verify scope is an accepted deliverables.